Your email has been sent!
Client: Buckingham Group Contracting Ltd (Network Rail).
Project: 19,690m3 of contaminated soil remediation at the Buxton Sidings site, part of Network Rail infrastructure
Brief: The client BGCL, were commissioned by Network Rail to construct a 550 metre railway siding, enabling longer freight trains to operate at this site. The legacy of the proposed route had been a heavily contaminated tip and the primary hazard was asbestos. Adhering to a detailed remediation strategy, Maylarch were contracted to cut through the site, safely dealing with all the contaminants present, including Japanese Knotweed.